Egypt: Benban Solar-04

Date Filed
24 Jun 2022
Status
Closed
Phase
Dispute Resolution (DR)
Country
Egypt, Arab Republic of

Case Tracker

Eligibility
Eligibility
Assessment
July 26, 2022-January 30, 2023
Assessment
Dispute Resolution
Dispute Resolution
January 30, 2023-April 23, 2024
Monitoring
April 24, 2024-June 27, 2025
Closed
Status as of June 27, 2025
Compliance
CURRENT Status
Closed(DISPUTE RESOLUTION)
Status as of June 27, 2025

Complaint Overview

Complainant

Community member

Concerns

Labor issues

Cross-Cutting Issues
Community Health and Safety Labor

Project Information

Region
Africa
Institution
IFC/MIGA
Name & Number
Benban Solar Park Project - 37633, 40386, 40390, 37636, 37637, 39728, 37580, 40019, 37713, 37591, 39995, 39997, 39729 (IFC) 14043, 14059, 14080, 14516, 14517, 14518, 14519, 14520, 14521, 13956, 13952, 13971 (MIGA)
Company
Benban Solar Park
Sector
Infrastructure
Department
Infrastructure
Category
B
Commitment

$225 million Equity

Synopsis

Project Overview

The Benban Solar Park is a 36-square-kilometer area composed of 32 operational energy-generating power plants operated by different companies near the village of Benban in Egypt. IFC provided a debt package of $225 million, which supports the construction of 13 of the 41 solar power plants that form the Benban Solar Park. MIGA has 12 active guarantees for projects in the Benban Solar Park.

Complaint

In June 2022, CAO received a complaint from a community member of a village in Benban, Egypt, citing concerns related to unfulfilled commitments regarding a development plan for the village, which had neither been distributed to nor consulted with the community.

Action

In July 2022, CAO found the complaint eligible and conducted an assessment. During CAOs assessment, the complainant and the Benban Solar Park representatives agreed to engage in a voluntary CAO-led dispute resolution process to address the issues raised in the complaint. In accordance with the CAO Policy, the case was transferred to CAO’s Dispute Resolution function in January 2023. The Assessment Report is available in English and Arabic.

In April 2024, the parties reached and signed a full settlement agreement as a result of the voluntary dispute resolution process, and the case was transferred to dispute resolution monitoring. CAO monitored the implementation of the agreement until February 2025. 

In June 2025, following the full implementation of the agreement, CAO closed the case. The Dispute Resolution Conclusion Report is available in English and Arabic.

Status

CAO closed the case after monitoring full implementation of the dispute resolution agreements.

Status as of June 27, 2025

Case Documents

  • Assessment Report(s)
    CAO Assessment Report - Egypt: Benban Solar 04
    Jan 30, 2023
    English
    CAO Assessment Report - Egypt: Benban Solar 04
    CAO Assessment Report - Egypt: Benban Solar 04 - Arabic
    Jan 30, 2023
    Arabic - اَلْعَرَبِيَّةُ
    CAO Assessment Report - Egypt: Benban Solar 04 - Arabic
  • Dispute Resolution

    Conclusion Report
    Conclusion Report
    Jun 27, 2025
    English
    Conclusion Report
    Conclusion Report
    Jun 27, 2025
    Arabic
    Conclusion Report