Guatemala: CIFI-01/ Hidro Santa Cruz

Date Filed
16 Jul 2015
Status
Open
Phase
Compliance
Country
Guatemala

Case Tracker

Eligibility
July 16, 2015-August 12, 2015
Eligibility
Assessment
August 12, 2015-May 18, 2016
Assessment
Dispute Resolution
Compliance
Appraisal
May 18, 2016-August 12, 2016
Investigation
August 12, 2016- December 19, 2018
Monitoring
Status as of June 11, 2020
CURRENT Status
Monitoring (COMPLIANCE)
Status as of June 11, 2020

Complaint Overview

Complainant

Local residents of Santa Cruz

Concerns

Community health & safety, information disclosure & consultation, Indigenous People, and cultural heritage

Cross-Cutting Issues
Risk Management Community Health and Safety Land Resettlement Indigenous Peoples Land Water Women Social Order / Conflict Coercion Violence / Abuse GBVH Loss of Life Project Benefits IFC/MIGA Due Diligence IFC/MIGA Supervision

Project Information

Region
Latin America and the Caribbean
Institution
IFC
Name & Number
IFC Project No. 26031
Company
Corporación Interamericana para el Financiamiento de Infraestructura, S.A. (CIFI)
Sector
Financial Institutions
Department
Global Practice - Finance & Markets
Category
FI
Commitment

US$20 million A Loan and US$10 million equity investment

Synopsis

Project Overview

In 2008, IFC invested in Corporación Interamericana para el Financiamiento de Infraestructura, S.A. (CIFI), a non-banking financial institution that supports small and medium infrastructure projects in Latin America and the Caribbean. In 2011, CIFI invested in Hidro Santa Cruz (HSC) for the construction of the Canbalam hydropower plant in Guatemala. However, in 2012, the project was suspended shortly after construction commenced. In November 2015, CIFI terminated its loan to the project developer, and the project was abandoned in December 2016.

Complaint

In July 2015, CAO received a complaint submitted by community representatives in Santa Cruz Barillas, alleging that the Canbalam hydropower project had not undergone proper consultation with Indigenous communities.

Complainants also claimed that opposition to the project resulted in violence and repression from both the company and the government, highlighting a specific incident on May 1, 2012, where one community member was killed, and two others were injured. The complainants believed that a security guard hired by the project was involved. HSC acknowledged that one of the individuals charged with the shooting had worked previously for their security contractor but denied any involvement.

Action

In August 2015, CAO found the complaint eligible and conducted an assessment visit in October 2015. Following the CAO assessment, the case was transferred to CAO’s Compliance function. In August 2016, CAO released a Compliance Appraisal Report concluding that an investigation was warranted in response to the complaint.  

In December 2018, CAO concluded its compliance investigation and submitted the report, along with IFC's response, to the President of the World Bank Group for approval. The report and response were reviewed during a meeting of the IFC Board in February 2020, leading to a revision of IFC's response. The revised response, dated April 2020, contained additional information that was not previously provided to CAO during the investigation.  

In June 2020, CAO published its Compliance Investigation Report and IFC's response after receiving clearance from the President. The report highlighted multiple instances of IFC's non-compliance regarding its review and oversight of the investment in CIFI, particularly in relation to the incident involving the Canbalam power plant sub-project.   

CAO's investigation found that IFC's pre-investment environmental and social (E&S) review of the company's E&S management system (ESMS) did not adequately match the level of risk involved. CAO identified deficiencies in IFC's evaluation of both the client's past performance in implementing the ESMS and their ability to meet IFC's standards in implementing the ESMS.  

IFC's failure to properly oversee the implementation of an adequate ESMS by the client resulted in a situation where project activities began without a thorough risk assessment and the implementation of necessary mitigation measures outlined in IFC's Performance Standards (PS). This lack of oversight contributed to the inadequate assessment and monitoring of risks and impacts associated with investments in projects like Canbalam.   

After the violent incidents in May 2012, the client halted disbursements to the project and informed IFC. According to IFC's own E&S procedures, IFC had a responsibility to respond to serious incidents at the project level. This involved assessing the root cause of the incident and implementing measures to prevent its recurrence.  

However, IFC failed to engage with the client regarding the project or the violent incident, contrary to its E&S procedures. CAO's investigation revealed that IFC did not comply with its procedures for responding to serious incidents and did not take the necessary steps to ensure that the client's response aligned with the PS requirements for addressing project impacts throughout the project cycle, including at project closure.  

The complainants argued that the project has had negative social effects on their communities. They specifically claimed that the project caused an increase in conflicts related to the project, resulting in the death of one community member, severe injuries to two others, and the detention of 17 additional community members. They also asserted that the construction of a perimeter fence around the project site has restricted their traditional access to land and natural resources.  

Despite the project being abandoned in December 2016, there is evidence to support the complainants' claim that residual impacts still exist. IFC, being aware of these impacts during the financing period, failed to communicate with its client to ensure that these residual impacts were properly assessed, minimized, mitigated, or compensated for as required by IFC's PS and Sustainability Policy, particularly during project closure.  

CAO Monitoring Reports
In May 2024, CAO completed its first Monitoring Report (included in the Q3, FY2025 Omnibus Monitoring Report, available in English and Spanish) on the case and decided to close project-level monitoring. This decision was made because IFC did not commit to any project-level actions in response to CAO's findings, and CIFI had already exited the sub-project investment several years ago. As a result, there is no expectation of further action from IFC to address the remaining impacts of the project. However, CAO continued to monitor four out of the five systemic commitments made by IFC in response to the investigation findings.   

In April 2026, CAO released its second Monitoring Report (included in the Q3, FY2026 Omnibus Monitoring Report, available in English and Spanish). CAO noted progress on IFC’s systemic commitments made in response to the investigation. CAO noted that IFC developed and commenced implementation of an institutionwide Approach to Responsible Exit, effective September 30, 2024, following internal review, public consultation, a pilot phase, and engagement with the World Bank Board. While CAO acknowledged these steps, it noted the significant time that had passed since IFC’s original commitment to commence implementation by December 31, 2020, and determined that it was too early to verify the effective implementation of the approach. 

CAO further noted that IFC finalized guidance for financial intermediary (FI) clients on incident response in October 2025 and revised its Environmental and Social Review Procedures (ESRP) in January 2025 to strengthen procedures for responding to significant adverse E&S incidents at both project and FI sub-project levels, including enhanced E&S expertise for complex FI portfolios. Given the recent implementation of these measures, the absence of cases triggering these procedures to date, and ongoing monitoring of IFC’s Responsible Exit Framework (RAF) and related FI guidance, CAO will continue to monitor these actions to assess their effectiveness over time, and the case remains under compliance monitoring.

Status

This case is under compliance monitoring.   

Status as of April 15, 2026.  

 

Case Documents

  • Complaint
    Letter of Complaint
    Jul 01, 2015
    English
    Letter of Complaint
    Assessment Report
    Assessment Report
    May 18, 2016
    English
    Assessment Report
    Assessment Report
    May 18, 2016
    Spanish
    Assessment Report
    Assessment Report
    May 18, 2016
    Qanjobal
    Assessment Report
    IFC Response to Assessment Report
    May 01, 2016
    English
    IFC Response to Assessment Report
  • Compliance

    Appraisal Report
    Compliance Appraisal Report
    Aug 12, 2016
    English
    Compliance Appraisal Report
    Compliance Appraisal Report
    Aug 12, 2016
    Spanish
    Compliance Appraisal Report
    Compliance Appraisal Report
    Aug 12, 2016
    Qanjabal
    Compliance Appraisal Report
    Terms of Reference
    Terms of Reference
    Jan 03, 2017
    English
    Terms of Reference
    Terms of Reference
    Jan 03, 2017
    Spanish
    Terms of Reference
    Investigation Report
    Investigation Report
    Dec 19, 2018
    English
    Investigation Report
    Investigation Report
    Dec 19, 2018
    Spanish
    Investigation Report
    Investigation Report Summary
    Sep 23, 2020
    Qanjabal
    Investigation Report Summary
    IFC Management Response and Management Action Plan
    Apr 23, 2020
    English
    IFC Management Response and Management Action Plan
    IFC Management Response and Management Action Plan
    Apr 23, 2020
    Spanish
    IFC Management Response and Management Action Plan
    Monitoring Report(s)
    First Monitoring Report (Q4 FY2024 Omnibus Report)
    May 01, 2024
    English
    First Monitoring Report (Q4 FY2024 Omnibus Report)
    First Monitoring Report (Q4 FY2024 Omnibus Report)
    May 01, 2024
    Spanish
    First Monitoring Report (Q4 FY2024 Omnibus Report)
    Second Monitoring Report (Q3 FY2026 Omnibus Report)
    Mar 31, 2026
    English
    Second Monitoring Report (Q3 FY2026 Omnibus Report)
    Second Monitoring Report (Q3 FY2026 Omnibus Report)
    Mar 31, 2026
    Spanish
    Second Monitoring Report (Q3 FY2026 Omnibus Report)
  • Close Modal

    Join Our Mailing List

    Get CAO’s newsletter, latest publications, event updates, and more.